Customers and sales
Projects
Projects are for planned work that is bigger than a ticket: onboarding a customer, a server migration, an office move. A project has phases, tasks, a team, a budget, and its own time and charges.
The Projects list
Open Projects. Each row shows the project number, name, company, lead, status, health, percent complete, hours worked against estimate, and end date.
The side panel has two groups:
- Views: All open, Active, My projects, On hold, Complete, Templates and Everything.
- Type: Any type, Client, Internal or Proposal.
Above the grid you can also filter by status, lead and company, and search with the module bar. The grid exports to CSV.
Status and health
A project's status is something you set: New, Active, On hold, Complete or Cancelled.
Health is worked out for you from hours, dates and progress:
| Health | When |
|---|---|
| On track | Nothing below applies. |
| At risk | Progress is falling behind the schedule or the hours used. |
| Late | The end date has passed. |
| Over budget | More hours have been worked than were planned. |
| Not started | Status is New and no time has been logged. |
| Paused | Status is On hold. |
| Closed / Cancelled | Status is Complete or Cancelled. |
Create a project
- Click New project (or + New → Project).
- To start from a template, choose one under From template. Its phases and tasks are copied, and their dates shift so the template's first day lands on your start date. Leave it on Blank project to start empty.
- Enter a Name and choose the Company. Both are required.
- Set Type, Status and Project lead.
- Optionally link a Contract. The contract's role rates are used to value time in the budget comparison.
- Enter Start and End dates, Estimated hours, Budget revenue and Budget cost.
- Click Create project.
Projects can also be created automatically when you accept a quote. See Opportunities, quotes and to-dos.
Templates
A template is a project whose Type is Template. Build the phases and tasks once, then reuse them. Templates appear under Views → Templates. To use one, open it and choose New project from this template from the ⋯ menu, or pick it under From template when creating a project.
The project record
The header shows the status, health and type, with the company, lead, dates, contract, hours and percent complete. Use Phase and Task to add to the plan. The ⋯ menu changes the status (for example Set active, Set on hold, Complete project).
If you complete a project that still has open tasks, you are asked to confirm with Complete anyway.
| Tab | Contents |
|---|---|
| Summary | Details, status notes, budget vs actual, and the next tasks due. |
| Schedule | The phase and task tree with a timeline. |
| Tasks | All tasks as a grid or a board. |
| Team | The people on the project and their billing roles. |
| Time | Time logged against the project's tasks. |
| Charges | Hardware, licences and other materials billed on the project. |
| Notes | Notes, calls, meetings and to-dos for the project. |
| Attachments | Uploaded files such as statements of work and diagrams. |
Summary
Click a value in the Details panel to edit it. If you leave Estimated hours empty, the estimate is the sum of the task estimates. Use Status detail for a short update on where things stand.
Budget vs actual compares three things, each as a pair of bars:
- Hours: worked against estimate.
- Revenue: billable value against budget revenue.
- Cost: labour and charges against budget cost.
A bar that runs over its plan turns red and is labelled "over". Underneath you get labour value, charges, labour cost, charge cost, margin and remaining work, and a breakdown of billable hours by role.
Next up lists the open tasks that are due soonest.
Schedule
The left side is a tree of phases and their tasks, with who is assigned, status, estimated hours and remaining hours. The right side is a week-by-week timeline with a bar for each task, a summary bar for each phase, and a marker for today.
- Bars are coloured by state: Complete, In progress, Not started or Late. An in-progress bar fills according to hours logged.
- A line links each task to its predecessor.
- Click a phase's arrow to collapse it, or use Collapse all / Expand all.
- Click a phase name to rename or delete it. Deleting a phase leaves its tasks on the project without a phase.
- Click + on a phase row to add a task to that phase.
- Click a task or its bar to open it.
Phase dates and hours are rolled up from the tasks inside them, so you never set them directly.
Limit: You cannot drag bars on the timeline. Change a task's dates in the task panel.
Tasks
Switch between Grid and Board. Your choice is remembered. Completed tasks are hidden until you tick Show complete.
On the board there is one column per task status (New, In progress, Waiting and Complete as standard). Drag a card to another column to change its status.
A task that is waiting on an unfinished predecessor shows an after T-number tag. Tasks flagged as issues show an issue tag.
Team
Click Add member, choose a Resource, and optionally a Project role. Leave the role empty to use the person's default role. The grid shows each member's rate, open tasks, remaining hours and worked hours. Removing someone from the team leaves their task assignments and logged time as they are.
Time
This tab is read-only. It shows a total by resource and every time entry on the project's tasks, with worked hours, hours to bill and approval status. Export it to CSV from the grid. To add time, log it on a task (below) or from your timesheet. See Time and expenses.
Charges
Click Add charge to record materials. Enter a Name, or pick a Product to fill in the name and price. Set Quantity, Unit price, Unit cost, Status, and whether it is Billable and Taxable. Once a charge has been posted to billing it can no longer be edited or deleted here.
Working with tasks
Click Task in the header, or click any existing task, to open the task panel.
- Enter a Title.
- Set Status and Assigned to.
- Choose a Billing role and Work type so that time logged on the task bills correctly.
- Choose a Phase and Priority.
- Set Start and End dates and Estimated hours. Update Remaining hours as work progresses.
- Optionally choose a Predecessor.
- Tick This is an issue (a problem blocking the project) to flag a blocker. The project header shows a count of open issues.
- Click Create task or Save.
For an existing task, the top of the panel shows hours Logged, Estimate and Remaining, with a projected total. Use Start timer to start the timer on the task, or Log time to enter time straight away.
Completing a task sets its remaining hours to zero. A task that has time logged against it cannot be deleted; complete it instead.
Predecessors
A predecessor is a task that must finish first. A task cannot be set to Complete while its predecessor is still open. If you try, the panel tells you which task is holding it up. The task panel also lists the task's successors, the tasks that are waiting on it.
My tasks
Projects → My tasks lists the open tasks assigned to you across all open projects, grouped by project. The header shows how many tasks you have and the total hours remaining.
Filter with All open, Overdue, Due in 7 days or Issues. For each task you can change the status from the drop-down, start the timer, or click Log time. Click the task to open it in its project.